蒲公英 - 制药技术的传播者 GMP理论的实践者

搜索
查看: 776|回复: 1
收起左侧

[文献分享] FAT, SAT & Commissioning Activities, Oh My!

[复制链接]
药士
发表于 2022-2-23 13:24:28 | 显示全部楼层 |阅读模式

欢迎您注册蒲公英

您需要 登录 才可以下载或查看,没有帐号?立即注册

x
Factory Acceptance Testing, Site Acceptance Testing& Commissioning Activities, Oh My!
Execution of factory acceptance testing (FAT) and siteacceptance testing (SAT) is a business-critical activity when it comes tocommissioning of a new system or equipment. The International Society forPharmaceutical Engineering (ISPE) defines FAT and SAT as the inspection andstatic and/or dynamic testing of manufacturing systems performed to approve thesystems for delivery and to support qualification of the systems.1FAT is conducted at the equipment manufacturer’s site and SAT at the final siteof installation.
FAT Is Key To Minimizing Downstream Issues
New biopharmaceutical equipment is customized anddesigned to fit the manufacturing operations model and product types beingproduced.  The complex nature of the systems, the technology, and theintricacies associated with meeting business and regulatory expectationspresent constant challenges during the commissioning phase. Eliminating issuesand errors up front allows you to minimize the number of business compromisesthat need to be made downstream. Unique requirements, such as accommodating theequipment’s dimensions for existing site drainage, piping, or room dimensions,need to be identified and addressed prior to shipment. In addition, new issues,such as position of the handle for accessibility, etc., can be identified whenFAT is performed. The costs of addressing such issues, whether simple orcomplex, grow once shipped from the equipment manufacturing site. Given theintricacies of advanced technology, FAT is also the right place to verifysoftware design specification, interface, and device integration.
A thorough assessment of the new unit post design andfabrication certainly reduces commissioning issues, which adds a definitivebusiness value. However, to effectively measure the return on investment,businesses should entrust the same team with all commissioning activities, i.e.,FAT, SAT, and commissioning. The metric should consider the number of issuesobserved post FAT in relation to the man-hours invested in the FAT and SATactivities. Addressing the issues at the equipment manufacturer’s site has aplethora of advantages, such as ease of sourcing components, quality ofequipment/instrument used to test and correct, cost, etc. A FAT includes checksfor safe access, interlocks, flow chart machine functions, orientation of dooropening, equipment dimension, utility fittings, piping lengths, closeness,sensors, testing tamper resistance/seals, electrical requirements, anddocumentation such as hardware design specifications, drawings, andcertificates. These aspects primarily relate to functionality, safety, fitnessto user requirements, compliance of the system to GMPs, and data integrity. Itis common to find inconsistencies post fabrication since there arepossibilities of misses during translation of all the user requirementspecifications (URS) and purchase order commitments into design/fabrication. Anexample is the use of a typical coated surface instead of a stainless-steelfinish for environmental chambers. The product impact could be minimal since itis strictly used for storage of the unit’s post-secondary packaging. However,there could be an impact on the cleaning procedure that might be appliedon-site. Making such changes at the installation site is impractical; hence,FAT is a must-do step versus nice to do, for critical systems.
FAT provides the opportunity for the equipment owner’srepresentatives to meet the equipment manufacturer’s expert teams, and theknowledge shared during the FAT sessions is critical to the long-term successof the commissioning process, i.e., through training. Identifying and involvingthe FAT team thus becomes critical. The test runs during FAT also providefirst-hand experience observing the unit running. Identifying and resolving thepunch list items during performance of the FAT allows for authorizing shipmentof the equipment to site. This is a critical milestone prior to SAT; hence, itshould only be completed by an authorized, trained, and approved subject matterexpert.
Figure 1: FAT and SAT
Upon receipt at the site and successful installationverification, critical aspects of the FAT are typically verified in the siteenvironment through a SAT, including the interfaces and monitoring devices[Figure 1]. Utility capacity, automation, interface, and control issues/gapsusually are highlighted during this stage. Therefore, additional test cases toverify the potential failure modes need to be integrated into the SAT protocol.
Use A Responsibility Matrix For Optimal Efficiency
The off-site FAT, on-site SAT, and commissioningactivities need careful planning for flawless execution. The commissioning2and qualification plan (CQV plan) needs to be adjusted based on the extent ofreliance on third parties for equipment expertise, test execution,commissioning project management, regulatory expertise, quality, automation,lab testing, etc. Table 1 provides guidance on the checks and balances requiredwhen utilizing external services for commissioning. A responsibility matrixprovides clarity and ensures ownership of activities, along with optimalutilization of internal and external subject matter experts.
Table 1: Example - Balanced Responsibility Matrix
  
FAT/SAT Activity
  
  
Execution Responsibility Matrix
  
  
Equipment Manufacturer (Vendor)
  
  
Approved External SME (Contractor)
  
  
Customer Organization
  
  
Scoping, identifying codes and regulatory references
  
  
Provide supporting evidence
  
  
Draft and/or review, provide SME inputs.
  
  
Drafted and/or approved by regulatory compliance
  
  
User requirement specification (URS)
  
  
Provide consultation.
  
  
Draft and/or review, provide SME inputs.
  
  
Drafted and/or approved by user department
  
  
Data sheet
  
  
Provide per client URS requirement.
  
  
  
Review, provide SME inputs for revisions where  needed.
  
  
Review and approval by internal engineering and  stakeholder departments.
  
  
Drawings
  
  
Provide per client design requirements.
  
  
Review support.
  
  
Review and approval by internal engineering.
  
  
FAT inspection/test plan/protocol
  
  
Draft and review.
  
  
Collaborate with vendor to finalize the plan.  Provide SME inputs.
  
  
Collaborate, review, and approve by internal  engineering and stakeholder departments.
  
  
Operating Procedures
  
  
Provide operating manual.
  
  
Draft and/or provide SME inputs.
  
  
Internal user department and stakeholders draft  and/or approve.
  
  
Calibration records
  
  
Perform calibration and provide records.
  
  
Perform on-site calibration where required and  provide records.
  
  
Perform on-site calibration and/or approve  calibration reports.
  
  
Calibration schedule
  
  
NA
  
  
Provide calibration frequency justification.
  
  
Develop calibration schedule and maintain.
  
  
Certificates, material of construction, finish etc.
  
  
Provide certificates
  
  
Verify and provide SME input.
  
  
Verification and acceptance.
  
  
Raw data review
  
  
Vendor’s internal QA.
  
  
On-site verification support.
  
  
Reviewers and QA.
  
  
Participation
  
  
Vendor PM, technologists, SME
  
  
On-site or virtual execution support.
  
  
Engineering, qualification, and user departments.
  
  
Inspection: Ex. weld, name plate, drain, dimensions,  documents
  
  
Vendor technologists, SME.
  
  
On-site or virtual execution support.
  
  
Engineering, qualification, and user departments.
  
  
Tests: Ex. pressure, vacuum, component  functionality, controls.
  
  
Vendor technologists, SME.
  
  
On-site or virtual execution support.
  
  
Engineering, qualification, and user departments.
  
  
Data integrity review
  
  
Vendor QA.
  
  
On-site verification.
  
  

  
  
Punch list resolution
  
  
Vendor PM, technologists, SME.
  
  
Verify and provide SME input.
  
  
Internal user department, engineering, and  stakeholder approval.
  

Defining The Goals In A CQV Plan & LeveragingCheckpoints
In addition to the responsibility matrix (includingresponsibilities of approved contractors), a CQV plan must have other criticalcomponents for transparency throughout the project and for robustness. The CQVplan should define the approach for the URS, system impact assessment (SIA),design specification (DS), hardware/software specification (HDS/SDS),functional risk assessment (FRA), FAT, SAT, commissioning, and qualification(IQ/OQ/PQ) documentation, traceability matrix, and stage gate requirements foreach equipment. In addition, the approach to deviation and change managementduring commissioning and qualification must be defined in the plan. The siteengineering team should be responsible for commissioning and validation of thequalification activities. They can rely on project managers and consultants todrive the project and to provide status updates. Where required, the samplingplan needs to be statistically justified by a trained statistician, asstipulated by guidance.3 Different approaches can be taken whenqualifying direct and indirect impact systems. It must be verified that alltest methods/procedures used are qualified prior to use.
To apply a risk-based approach,4 thereneeds to be documented justification at each stage that would withstand anyregulatory scrutiny. It has been found that 45% of the data integrity issues inwarning letters were associated with operations related data.5 Newproduction equipment, with a substantial amount of automation, monitoring,parameters, and attributes, generates critical data. Data governance, control,and assurance of traceability and integrity need to be considered during earlycommissioning.  The controls become even more critical when risk-basedleveraging is applied. Though the CQV plan can potentially identify leveragingopportunities, the outcome of the test cases and the integrity assurance of thevendor-provided data need to be considered prior to officially accepting thetest to be leveraged. Adequate stage gate documented decision steps need to beintegrated into a concise CQV plan.
Conclusion
Developing your FAT and SATplans executing them, and maintaining integrity throughout the process requirescareful, meticulous planning and continual re-evaluation of the plan. This iseven more critical during the pandemic, when teams work across the globevirtually and activities are fast tracked. The development of a fit-for-purposeCQV plan with a clear definition of vendor and contractor roles andresponsibilities,6 continual reconfirmation against the plan afterevery critical execution, providing justification of any changes to the plan,and incorporating enough stage gate points for the assessment are key aspectsto be considered. The goal is to assure traceability and maintain integritythroughout the project, where multiple external parties are involved, bothvirtually and on-site. Where enough supporting evidence is not available, thestrategy on leveraging needs to be reconsidered. It is also ideal to have the teamgoals and responsibilities established. Maintaining the team until the CQVplanned activities are complete is critical since much knowledge may remaintacit in a fast-paced commissioning scenario. Adequate mechanisms need to be inplace within the CQV plan to document and convert the tacit knowledge intointernal explicit knowledge at the earliest opportunity. Applying the insightsdiscussed in this article can add value and greatly reduce potential downstreamissues during a critical CQV project.
回复

使用道具 举报

药徒
发表于 2022-2-23 15:44:07 | 显示全部楼层
想知道什么出处?
回复

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

本版积分规则

×发帖声明
1、本站为技术交流论坛,发帖的内容具有互动属性。您在本站发布的内容:
①在无人回复的情况下,可以通过自助删帖功能随时删除(自助删帖功能关闭期间,可以联系管理员微信:8542508 处理。)
②在有人回复和讨论的情况下,主题帖和回复内容已构成一个不可分割的整体,您将不能直接删除该帖。
2、禁止发布任何涉政、涉黄赌毒及其他违反国家相关法律、法规、及本站版规的内容,详情请参阅《蒲公英论坛总版规》。
3、您在本站发表、转载的任何作品仅代表您个人观点,不代表本站观点。不要盗用有版权要求的作品,转贴请注明来源,否则文责自负。
4、请认真阅读上述条款,您发帖即代表接受上述条款。

QQ|手机版|蒲公英|ouryao|蒲公英 ( 京ICP备14042168号-1 )  增值电信业务经营许可证编号:京B2-20243455  互联网药品信息服务资格证书编号:(京)-非经营性-2024-0033

GMT+8, 2025-2-18 00:42

Powered by Discuz! X3.4运维单位:苏州豚鼠科技有限公司

Copyright © 2001-2020, Tencent Cloud.

声明:蒲公英网站所涉及的原创文章、文字内容、视频图片及首发资料,版权归作者及蒲公英网站所有,转载要在显著位置标明来源“蒲公英”;禁止任何形式的商业用途。违反上述声明的,本站及作者将追究法律责任。
快速回复 返回顶部 返回列表